Buckingham - Winslow Cycleway Extension (Phase 2) Construction

Bulletin #001 - 18/03/2019
Dear Residents and Businesses,
 
Welcome to the first information Bulletin for the Buckingham to Winslow Cycleway Extension Scheme (Phase 2) providing progress and works information on the implementation of the scheme.

Introduction:

The Buckingham to Winslow cycleway extension scheme is a continuation of the cycling and walking improvements already completed along the A413 from Winslow town centre to the Lace Hill roundabout in Buckingham. The scheme will complete the link between Winslow and Buckingham town centres. The scheme is funded by developer contributions of £350,000.

The extension scheme is being delivered in two phases. Construction of Phase 1 of the scheme
, linking London Road with the town centre through Badgers estate, Cornwalls Meadow and Stratford Fields was completed in September 2018.

 
Construction of Phase 2 of the scheme – a shared cycle-footway on the western side of A413 London Road providing connections to the Swan Pool, The Buckingham School and The Royal Latin School – will commence on 27 March 2019. It is anticipated that the construction works will take approximately 10 weeks to complete. 

For further information please view the project webpage www.buckscc.gov.uk/buckinghamcycleway
Construction Programme:

The construction works will be carried out along the A413 London Road, Buckingham to create the new formal route for Phase 2, connecting to the Swan Pool Leisure Centre, the Buckingham school and the Royal Latin school. To view the Phase 2 overview plan click here.
Key notes
  • Construction will take place only on weekdays (Monday to Friday)
  • Weekday working hours start from 9:30am to 3:30pm daily (with the exception of Bank Holidays)
  • Construction works planned to start 27 March 2019
Expected completion date of works is end of June 2019.
The following sections of Phase 2 footway work are planned as follows*:
Additional Information
  • Information signs will be erected to highlight the planned works, dates and duration.
  • The work will be undertaken using 2-way temporary signals and road / footway narrowings as necessary depending on the location of the works. During the works some delays may be unavoidable for road users.
  • During the works access will be maintained for residents. However, on occasions for health and safety reasons, road users may be requested to wait temporarily to enable completion of a particular operation/activity by the contractor. We apologise for any inconvenience this may cause.
  • We will endeavour to keep construction noise levels on the site as low as possible. However, due to the nature of these works some noisy activities will be required so we apologise for this in advance
Contacts:
For any queries regarding the works during weekdays, contact Adrian Lane (T-ALANE@buckscc.org) at Transport for Buckinghamshire. 

Buckinghamshire County Council has a dedicated mailbox for the Buckingham to Winslow cycleway extension project at hitmailbox@buckscc.gov.uk and we welcome emails and queries about the project. You can also contact the Highways Infrastructure Team on 01296 382416.
Emergency Contact Number - Transport for Buckinghamshire Out of office (Highways): 01296 486630.Further e-Bulletins will be provided on a regular basis.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Buckinghamshire County Council · Walton Street · Aylesbury, Buckinghamshire HP20 1UA · United Kingdom

Email Marketing Powered by Mailchimp