Heron Resources Quarterly Report March 2019

HIGHLIGHTS

Woodlawn Zinc-Copper Project Development Progress

Plant Construction

  • Overall EPC completion at 99% and process plant commissioning at 77%
  • Construction work completed
  • Commissioning with reclaim tailings ore from Tailings Dam South on a 24 hour basis
  • Concentrate production imminent

Underground

  • 1.3km of underground development completed
  • Raiseboring of the primary ventilation shaft completed from surface
  • First ore from underground delivered to ROM

Retreatment

  • Hydraulic mining transitioning to production mode
Woodlawn Exploration
  • An Induced Polarisation (IP) geophysical survey completed north of Woodlawn.  Significant chargeability and resistivity anomalies were detected; modelling of the data is being finalised.
Corporate
  • Cash: Heron held A$66.5 million in cash (including bonds of A$7.77 million) and A$2 million in investments as at 31 March 2019.
  • Sedgman Claim: Progress claims were received from Sedgman, Woodlawn EPC Contractor, in February and March which exceeded the agreed guaranteed maximum price contract value, both of which were rejected by the Contract Superintendent. No progress claim has been received in April.
For the full announcement, please click here
For further information regarding Heron Resources, please visit www.heronresources.com.au or contact:
Heron Resources
Mr Wayne Taylor
Managing Director and CEO
Tel: +61 2 9119 8111
Email: heron@heronresources.com.au
Twitter
Copyright © 2019 Heron Resources, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list

Email Marketing Powered by Mailchimp