May 6, 2022
We are continuing to condense these email updates to include only the most relevant information. We are working closely with residents and businesses to address impacts that may affect them.

Work continues to ramp up throughout the project corridor. Pay close attention for pedestrians, construction crews, equipment, and detour signage. 

Thanks to everyone for being mindful of our nighttime road closure on E Madison St this past Wednesday. Crews installed the first portion of a watermain in the intersection of 20th Avenue and E Madison St. We plan to return to this same intersection on May 15 to finish the work. We will fully close the roadway again at night.

Please continue reading for more updates including:
Work areas: 

Detours and lane reductions:
To make space for construction and to keep people traveling safe, our contractor regularly installs short- and long-term detours. The below list reflects planned detours for next week. We may need to make adjustments as work progresses based on site conditions and safety needs. 

Eastbound/Westbound Detours:
  • Traveling east (towards Madison Valley):
    • E Madison St closed between 12th and 13th avenues - Please follow signs to Union St, turn left at 13th Ave, and right to return to E Madison St
  • Traveling west (towards Downtown):
    • E Madison St closed between 12th and 13th avenues - Please follow signs to turn right at 15th Ave, left on E John St, left on 12th Ave, and right to return to E Madison.

 
Capitol Hill detour at Madison St and 12th Ave

Traffic reduced to one lane at:
  • E Madison St between 1st and 4th avenues
  • Spring St between 1st and 3rd avenues
  • Spring St between 7th and 9th avenues
  • E Madison St between Broadway and 13th Ave
  • E Madison St between 18th and 20th avenues
  • E Madison St between 24th and 25th avenues
Upcoming construction activities
Downtown: Street and sidewalk paving continue, including the following activities:
  • Weekend work May 6 – 8:
    • Intersection demo and paving on the northwest corner of Spring St and 3rd Ave
  • During the week of May 9:
    • Sidewalk installation on:
      • Spring between 2nd and 3rd avenues
      • 1st Avenue between E Madison and Spring streets on the west side
    • Roadway demo, repairs, and paving on the south side of Madison between 1st and 3rd avenues
  • Weekend work May 13 – 15*:
    • Paving in front of driveways on the south side of Spring St between 1st and 3rd avenues
  • During the week of May 16:
    • Sidewalk installation on continues (see above details)
    • Roadway demo, repairs and paving extend east on Madison up to 4th avenue
* The team plans to close the driveways and alleys from 7 PM Friday to 6 AM Monday.
First Hill: King County Metro to removing trolley power lines; demo/paving on Spring St between 7th and 9th avenues
  • During the week of May 9 & 16:
    • Demo/paving to on Spring St between 7th and 9th avenues
  • Weekend work in May:
    • King County Metro will remove existing trolley power lines on Madison St between 6th Ave and Broadway.
      • Drivers can expect temporary lane shifts/closures and intermittent delays while equipment is repositioned
Capitol Hill: Water/storm pipe installation continues; Full road closure on Madison between 19th and 22nd avenues planned for May 15: 
  • During the week of May 9:
    • Storm drain installation on Madison St between 12th and 13th avenues
    • Watermain work on Madison between 19th and 20th avenues
      • Nearby residents and businesses may experience temporary water outages May 12 – 14**
    • Pole foundation installation on Madison between Broadway and 13th
  • Weekend work May 13 – 15:
    • Roadway paving within the current closure on Pine St between 15th and 16th avenues east
    • Full closure on Madison St planned for the evening of May 15 between 19th and 22nd avenues east in coordination with Seattle Public Utilities
      • Nearby residents and businesses may experience a temporary overnight water outage as part of this work**
      • The road will close beginning at 7 p.m. and will reopen as early as 6 a.m.
  • During the week of May 16:
    • Watermain installation between 19th and 20th continues
    • Watermain installation on Madison St between Broadway and 11th Avenue starts
** For questions about water outages, visit SPU’s water outage map or call SPU’s 24/7 Operations Response Center at 206-386-1800
Madison Valley: Watermain installation on Madison St between 24th and 25th avenues
  • This work will take place during daytime work hours for the next couple of weeks.
Resource spotlight

Get Help with Your Utility Bills

If you’re behind on your utility bills, Seattle City Light (SCL) and Seattle Public Utilities (SPU) offer payment plans for all customers, including residential, business, renters, and property owners, regardless of income, and allow you to break up your past due balance into smaller payments and pay it down over time. 

Explore options today: seattle.gov/UtilityBillHelp
King County Metro bus stop closures or relocations
As construction activities continue, bus stops on Madison and Spring streets will temporarily close or relocate as needed. To learn more about these closures or relocations, please visit King County Metro’s Transit Alerts page.
Thank you for your patience during construction!
If you have concerns about accessibility or other issues with construction, please send us your address, contact information, and concerns so we can better understand and work together throughout construction. You can complete our construction survey in English, Chinese (traditional), Korean, or Vietnamese or you can reach us at MadisonBRT@Seattle.gov or call (206) 484-2780.

Want to learn more about the project? 

Visit our website to see what Madison St will look like once the project is complete.

Please share these weekly updates with others who may be interested and encourage people to subscribe on our webpage

Thank you!

Adonis Ducksworth – RapidRide G Line Outreach Lead
MadisonBRT@Seattle.gov
(206) 484-2780
seattle.gov/MadisonBusRapidTransit  
Text “MADISON” to 33222 to sign up for project alerts via text
Seattle Transportation Plan

We're engaging communities in developing the Seattle Transportation Plan. The plan establishes a renewed vision for the future of our streets and public spaces. Together, we’ll reimagine how we move through and enjoy Seattle’s streets.    

We are partnering with community-based organizations, who have relationships with the communities they serve, to listen and ensure that the plan reflects the values and needs of everyone. Visit our blog to learn more information and see the incredible organizations we are partnering with. 
For more information on the project, please visit our website.

If you have specific questions, or would like to schedule a meeting or briefing, please email us at MadisonBRT@seattle.gov or call us at 206-484-2780. 

Hadaaad mashruucan suaalo ka qabtit email noo soo dir:
MadisonBRT@seattle.gov ama nasoo wac: 206-484-2780.

Nếu bạn co cau hỏi về dự an, vui long gửi email cho chung toi theo địa chỉ
MadisonBRT@seattle.gov hoặc gọi cho chung toi theo số 206-484-2780.

如果您對本工程有任何疑問,請電郵 MadisonBRT@seattle.gov 或致電
206-484-2780.

यदिआपके पास प्रोजेक्ट के बारे में प्रश्न हैं, तोकृपया हमें MadisonBRT@seattle.
govपर ईमेल करें या हमें 206-484-2780 पर कॉल करें

이 프로젝트에 대한 질문이 있으시면, 이메일 MadisonBRT@seattle.gov 로
또는 206-484-2780로 전화 주십시요.

Si tiene preguntas sobre el proyecto, por favor envienos un mensaje a MadisonBRT@seattle.gov o llamenos al 206-484-2780
Copyright © 2022 Seattle Department of Transportation, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list

Email Marketing Powered by Mailchimp